Prepare for success in carpentry with the Red Seal Carpenter Practice Exam. Sharpen your skills, tackle challenging questions, and boost confidence for the Red Seal certification.

Each practice test/flash card set has 50 randomly selected questions from a bank of over 500. You'll get a new set of questions each time!

Practice this question and more.


What must be done to a dimensional lumber floor system to stiffen the joists?

  1. Install continuous stiffeners to all joists at 600 mm (2') o/c.

  2. Install vertical stiffeners to all joists at 600 mm (2") o/c.

  3. Install 2x4 blocks between joists at1800 mm (6') o/c max.

  4. Install cross-bridging between joists at 2100 mm (7') o/c max.

The correct answer is: Install cross-bridging between joists at 2100 mm (7') o/c max.

Cross-bridging should be installed between joists at 2100 mm (7') o/c max in order to stiffen the joists in a dimensional lumber floor system. This is because cross-bridging provides diagonal bracing between joists, preventing them from twisting or shifting. Options A and B may also provide some stiffness, but they are not as effective as cross-bridging. Option C, installing 2x4 blocks between joists, may actually add weight and cause additional sagging to the floor system. Therefore, option D is the best solution for stiffening joists.